Task Allocation Brief
Prepared By: [YOUR NAME]
Company: [YOUR COMPANY NAME]
I. Project Information
The project involves the development of a new website for our company. The goal is to create a modern, user-friendly platform that effectively showcases our products and services, improves customer engagement, and boosts online visibility.
II. Team Members
Sarah Johnson: Project Management, Requirement Gathering Mark Davis: Lead Developer, Backend Development, Frontend Development, Deployment Emily Chen: UI/UX Design, Design Wireframes, Design UI Elements, Frontend Development Alex Martinez: Content Writer, Write Website Content Chris Thompson: QA Tester, Quality Assurance
|
III. Task List
Task Name and Description | Start/End Date | Estimated Duration | Priority Level | Assigned Team Member(s) |
---|
Requirement Gathering: Gather requirements from stakeholders regarding website features and functionality.
| March 15, 2050 - March 17, 2050 | 3 days | High | Sarah Johnson |
Design Wireframes: Create wireframes for website layout and user interface.
| March 18, 2050 - March 21, 2050 | 4 days | High | Emily Chen |
Develop Backend: Develop the backend infrastructure of the website.
| March 22, 2050 - March 31, 2050 | 10 days | High | Mark Davis |
Design UI Elements: Design user interface elements such as buttons, icons, etc.
| March 22, 2050 - March 28, 2050 | 7 days | Medium | Emily Chen |
Write Website Content: Create compelling and informative content for the website.
| March 25, 2050 - March 29, 2050 | 5 days | Medium | Alex Martinez |
Frontend Development: Implement frontend design and integrate with the backend.
| March 29, 2050 - April 5, 2050 | 7 days | High | Mark Davis, Emily Chen |
Quality Assurance: Conduct thorough testing to ensure website functionality.
| April 6, 2050 - April 10, 2050 | 5 days | High | Chris Thompson |
Deployment: Deploy the website to the production environment.
| April 11, 2050 - April 12, 2050 | 2 days | High | Mark Davis |
IV. Dependencies
In the project workflow, completion of Design Wireframes is necessary before Frontend Development begins for a clear interface blueprint. Backend Development must conclude before Frontend Development to ensure seamless integration. Additionally, Website Content finalization precedes Deployment for accurate and compelling website information. These dependencies are vital for efficient progress.
V. Progress Tracking
Daily stand-up meetings to discuss progress and address any issues.
Weekly progress reports submitted by each team member.
Project management software to track tasks and milestones.
VI. Communication Plan
Employs various strategies to foster effective communication and collaboration. We hold weekly meetings to discuss progress and address concerns, utilize project management software for task tracking, and promptly communicate any issues via team chat or email to ensure timely resolution. These practices enhance transparency, accountability, and productivity within our team.
VII. Risks and Mitigation Strategies
Risk | Mitigation |
---|
Delays in requirement gathering due to unclear client expectations | Schedule regular meetings with stakeholders for clarification and feedback |
Technical issues during development may cause delays | Regular code reviews and testing throughout the development process |
Resource constraints leading to task backlog | Prioritize tasks based on project objectives and adjust resources as needed |