CONSTRUCTION ACCOMPLISHMENT REPORT
Reported by: [Your Name], Project Manager
Project Overview:
Project Name: Peoria Complex
Project Location: Peoria, AZ 85345
Start Date: January 15, 2050
Expected Completion Date: December 30, 2051
Scope of Work: Construction of 200 residential units, parking, and landscaping.
Accomplishments:
Task Completed | Date Completed |
|---|
Excavation and foundation work for Building 1 | October 15, 2050 |
Structural Framing for Building 1 | November 5, 2050 |
Plumbing installation for Building 1 | November 8, 2050 |
Site grading for parking area | November 10, 2050 |
Work in Progress:
Task In Progress | Expected Completion Date |
|---|
Framing for Building 2 | November 20, 2050 |
Electrical installation for Building 1 | November 25, 2050 |
Excavation for parking lot 2 | December 5, 2050 |
Issues or Delays:
Issue | Impact |
|---|
Delay in steel beam delivery for Building 2 | 5-day delay in framing work |
Rain delays for site grading | 7-day delay in foundation work |
Next Steps:
Task | Planned Date |
|---|
Start electrical & HVAC installation for Building 2 | December 1, 2050 |
Continue landscaping for Building 1 | December 10, 2050 |
Start framing for Building 3 | December 15, 2050 |
Conclusion:
The Peoria, AZ Complex is progressing well, with key tasks completed on schedule. A few minor delays have occurred, but they are being addressed, and the project remains on track. Future work will focus on the continued development of Building 2 and preparation for Building 3.